1. As per applicant request application, and further to the approval of Hon'able chairman on 24.12.2019,estimated finish date,has been extended from 31.05.2018 to 31.05.2019. The estimated finish date has been changed on 03/01/2020.Therefore the revised estimated finish date should be read as 31.05.2019. 2. The project has been extended beyond one-year w.r.t. Authority order dated 22-05-2020 on 03-07-2020. This bears the approval of Honorable Chairman, before extension beyond one year the estimated finish date of the project was 31-05-2019. 3. Revised maps with subsequent changes updated on 03-07-2020. Updated Building Plans uploaded in the "Building Sanction Plan" column.