1. As we are developing project in Phases, total area of project is 22374.35 Sq. Meter and Phase 1 area is 15094.897. As of the project has been approved Stilt+9 (27Meter) refer UIT letter dated 27/07/2017 enclosed herewith. Initially we have mentioned wrong area of Phase-1 (Block-A).Now we have mentioned the correct area & the balance amount is deposited through DD. Earlier Amount online Rs.35694/- & now Rs.1,15,255/- through DD. 2. The earlier project finish date was 31.05.2019 and now the estimate finish date has been extended to 31.12.2019. The estimated finish date has been approved and changed on 03.06.2019.As per remark the correct phase area has been rectified in Land Details of Registering Project.